TANGERANG - Ahead of Eid Al-Fitr 2024 homecoming, Soekarno Hatta Airport, Tangerang City continues to improve services, one of which is conducting electrical testing and backup systems at Terminal 1, 2, 3 and several KCU work buildings.
Senior Manager of Branch Communication & Legal, M. Holik Muardi explained, testing electricity networks and backup systems at Terminal 1, 2, 3 and several work buildings at KCU Soetta Airport to ensure the reliability of electricity supply and electrical system resilience in the face of increased movement.
"By testing the electricity system as a whole, potential problems can be identified and ensuring that operations and response times back up of spare power supply are ready to overcome them quickly and efficiently," Holik said in his statement, Thursday, March 28.
SEE ALSO:
In addition, Holik continued, this test included a 15-minute power outage and a 30-minute Genset On Load Test at two testing sessions. So that it can see the readiness and reliability of the backup system in overcoming the emergency situation at Soetta Airport.
"(Apart from that) to ensure that airport operations can run smoothly without interruption," he said.
The English, Chinese, Japanese, Arabic, and French versions are automatically generated by the AI. So there may still be inaccuracies in translating, please always see Indonesian as our main language. (system supported by DigitalSiber.id)