JAKARTA - Jasamarga Metropolitan Tollroad as the manager of the Cipularang and Padaleunyi Toll Roads carry out maintenance in the form of road hardening on the Cipularang and Padaleunyi Toll Roads from Monday, June 10 to Friday, June 14, 2024.

Senior Manager Representative Office 3 Jasamarga Metropolitan Tollroad Agni Mayvinna said, during repairs, lanes cannot be crossed. However, other lanes can still be used.

"The work of maintaining violence is in order to improve the quality of service to road users and to meet the Minimum Service Standards (SPM)," he said in his official statement, Monday, June 10.

Agni said that his party apologized for the inconvenience caused by the work.

He appealed to road users to anticipate travel routes in order to optimize the current traffic engineering and ensure the adequacy of electronic card balances before starting the trip to avoid overcrowding when transacting at toll gates.

"It is hoped that road users will always obey traffic signs and follow the directions of officers in the field," he said.

The work on the reconstruction of violence is as follows:

A. The construction work of the Cipularang section of the violence

The violent reconstruction will be carried out starting Monday, June 10, 2024 at 08.00 WIB. Open traffic on Friday, June 14, 2024 at 14.00 WIB.

- KM 76+234 to KM 76+249 in lane 1 along 15 meters;

- KM 84+133 to KM 84+168 in lane 1 along 35 meters;

- KM 84+188 to KM 84+208 in lane 1 along 20 meters;

- KM 84 + 233 to KM 84 + 402 in lane 1 along 10 meters.

1. Direction Jakarta

- KM 84 + 34 to KM 84 + 324 in lane 1 along 20 meters;

- KM 84+207 to KM 84+127 in lane 1 along 35 meters;

- KM 84+137 to KM 84+122 in lane 1 along 15 meters;

- KM 80 + 726 to KM 80 + 676 in lane 1 along 50 meters;

- KM 80 + 661 to KM 80 + 631 in lane 1 along 30 meters;

- KM 80 + 601 to KM 80 + 576 in lane 1 along 25 meters;

- KM 80 + 461 to KM 80 + 426 in lane 1 along 35 meters.

B. Collaborating construction work on the Padaleunyi Section

The violent reconstruction will be carried out starting Monday, June 10, 2024 at 08.00 WIB. Open traffic on Friday, June 14, 2024 at 14.00 WIB.

1. Direction Jakarta

- KM 121+528 to KM 121+483 in lane 1 along 45 meters;

- KM 121 + 450 to KM 121 + 384 in lane 1 along 66 meters;

- KM 121 + 364 to KM 121 + 3366 in lane 1 along 28 meters;

- KM 121+215 to KM 121+078 in lane 1 along 137 meters;

- KM 121 + 048 to KM 121 + 999 in lane 1 along 49 meters.

C. Overlay Filling Filling Work (SFO)

1. Cileunyi Direction

- KM 130 + 812 to KM 131 + 200 in lane 2 along 388 meters, carried out Wednesday, June 12, 2024 starting at 08.00 WIB to 17.00 WIB.

- KM 133 + 458 to KM 133 + 758 in lane 2 along 300 meters, carried out Thursday, June 13, 2024 starting at 08.00 WIB to 17:00 WIB.

2. Direction Jakarta

- KM 131+998 to KM 131+698 in lane 3 along 200 meters, will be held Monday, June 10, 2024 starting at 08.00 WIB to 17:00 WIB;

- KM 131 + 698 to KM 131 + 400 in lane 3 along 298 meters, carried out Tuesday, June 11, 2024 starting at 08.00 WIB to 17.00 WIB;

- KM 130+294 to KM 130+094 in lane 3 along 200 meters, will be held Friday, June 14, 2024 starting at 08.00 WIB to 17.00 WIB.