JAKARTA - The Luwuk 40 MW PLTMG Project Completion Order which stopped in August 2022, on March 17, 2023, was handed over to PLN Enjiniring to be continued.

The Board of Directors of PLN Enjiniring is committed to supporting PLN, especially PLN (Persero) North Sulawesi Development Main Unit in the completion of national strategic projects to illuminate the Banggai Regency area.

This statement was made by the President Director of PLNE, Chairani Rachmatullah during a working visit at the Banggai Regent's Government Office, Amirudin on Wednesday, August 16.

The PLTMG Luwuk 40 MW project located in Batui District, Banggai Regency, Central Sulawesi Province was built by utilizing gas sources from Batui District to strengthen the electricity system in Central Sulawesi, especially Banggai Regency and its surroundings.

The construction of the 40 MW Luwuk PLTMG is targeted to be completed and can start operating gradually so that it is expected to strengthen the electricity system in Central Sulawesi.

"Hopefully 2 power plants can operate in October 2023, so that it will immediately increase economic growth in Banggai," said Banggai Regent.


The English, Chinese, Japanese, Arabic, and French versions are automatically generated by the AI. So there may still be inaccuracies in translating, please always see Indonesian as our main language. (system supported by DigitalSiber.id)