JAKARTA - Jasa Marga through Jasamarga Metropolitan Tollroad which is the manager of the Jagorawi Toll Road together with PT Jasamarga Tollroad Maintenance (JMTM) as a toll road maintenance service provider, will carry out bridge repair work, periodic maintenance of scrapping filling overlay (SFO) and pavement reconstruction.
The maintenance of the toll road is a form of Jasa Marga's commitment to the comfort and safety of road users while driving.
General Manager Representative Office 1 Regional Jasamarga Metropolitan Tollroad, Tri Wahyu Subekti said that apart from Jasa Marga's efforts to meet minimum service standards (SPM), maintenance work is also carried out as an effort to improve the quality of roads and bridges.
"The work will be carried out from May 22 to May 27, 2022," he said in an official statement, Sunday, May 22.
VOIR éGALEMENT:
Tri explained that the lane that is the object of temporary maintenance cannot be crossed during the work, and some of the lanes closest to the maintenance object will be used for work areas and situational heavy vehicles.
Furthermore, Tri said, Jasa Marga, has prepared safety signs for work according to standards, alerted traffic control officers, and ensures officers maintain health protocols at work locations, for the safety of road users.
"Jasa Marga apologizes for the inconvenience caused by this work. Please contact the 24-hour Jasa Marga Call Center at telephone number 14080 if you need information and assistance on toll roads," he said.
The schedule and details of work locations are as follows:
Bridge Repair Works
Repair of the bridge at km 33+200 lane 1 in the direction of Ciawi, will be carried out on May 22, 2022, at 22.00 western Indonesia time until May 27, 2022, at 06.00 western Indonesia time.
"Repairs on the bridge km 24 + 000 lane 2 directions Jakarta, will be carried out on May 23, 2022, at 20.00 western Indonesia time until May 29, 2022, at 24.00 western Indonesia time," said Tri.
Periodic Maintenance Work/SFO
First, maintenance on KM 19+785 to KM 19+955 lane 2 Ciawi along 170 m, carried out Monday, May 23, 2022.
Then, at KM 23+050 to KM 23+150 lane 3 Ciawi along 100 m, it will be held Tuesday, May 24, 2022. Meanwhile, at KM 25+300 to KM 25+408 lane 2 Ciawi along 108 meters, it will be held on Wednesday, May 25, 2022.
"KM 25+620 to KM 25+727 lane 3-way Ciawi along 107 m, will be held Thursday, May 26, 2022. Meanwhile, KM 37+006 to KM 37+131 lane 3-way Ciawi along 125 meters will be held Friday, May 27, 2022, " he said.
Meanwhile, repairs at KM 35 + 115 to KM 34 + 950 lane 2 in the direction of Jakarta for 165 meters will be carried out on Saturday, May 28, 2022.
"SFO periodic maintenance work is carried out in the window time period from 22.00 to 05.00 western Indonesia time," he said.
Pavement Reconstruction Works
Meanwhile, the pavement reconstruction at KM 23+470 to KM 23+596 in the direction of Ciawi, lane 1 with a length of 126 meters, will be carried out on 22 May 2022 until open traffic on 27 May 2022 at 00.00 western Indonesia time.