Construction Of MRT Jakarta Phase 2A HI Roundabout-City Capai 19.68 Percent
JAKARTA - PT MRT Jakarta (Perseroda) noted that the progress of the construction of the MRT Jakarta Phase 2A Hotel Indonesia (HI)-City roundabout has reached 19.68 percent until February 15, 2023.
Head of the Project Management Division for Construction 1 MRT Jakarta Sony Desta Primandani said there were three packages (Contract Package/CP), namely CP 201, CP 202, and CP 203.
"I can convey, the overall progress until February 15, 2023, we obtained the overall process for Phase 2A at 19.68 percent," said Head of the Project Management Division for Construction 1 MRT Jakarta Sony Desta Primandani at a press conference at the MRT Office. Jakarta, Thursday, February 23.
Sony said the phase 2A project consisted of three parts, namely CP 201 HI-Harmoni Roundabout, CP 202 Harmoni-Mangga Besar, and CP 203 Mangga Besar-City.
The construction is also divided into two segments, namely segment 1 of the HI-Harmoni Roundabout and segment 2 of the Harmoni-City.
Based on data, MRT said that the progress of CP 201 reached 51.78 percent, CP 202 9.87 percent, and CP 203 27.13 percent.
Meanwhile, the progress of segment 1 reached 41.63 percent and segment 2 reached 10.44 percent. "So, on average for progress per package, we are still above the plan we have made," said Sony.
Meanwhile, CP 205 for the "railway system" and "track work" of the HI-Kota roundabout, said Sony, are still being tendered to this day.
"For CP 205 at this time we are still making tenders. We hope that in April, we will get the offer proposal from the tenders," he said.
Then, CP 206 for the "rolling stock" and CP 207 for the "automatic core collection system" are currently still in tender preparation.