PT Pertamina Hulu Energi reports that it has completed the 3D Offshore Seismic Survey in Eastern Indonesia, especially the Bone & Southeast (SE) Seram Region, at the end of June 2024.

Just so you know, the 3D Offshore Bone and SE Seram Seismics are part of the Work Commitment Pasti PHE Jambi Merang (KKPJM) in open areas conducted through PHE's subsidiary, PT Elnusa Tbk, which collaborates with China Oilfield Services Limited (COSL).

PHE Exploration Director, Muharram Jaya Panguriseng explained, the 3D Offshore Bone and 3D Seram Seismic Survey Projects were successfully implemented with Zero Accident and on time, on budget, on schedule and on return (Otobosor).

"The 3D Bone survey covering an area of 821 km2 can be completed within 26 days of the 37 day target and the 700 km2 Seram SE survey can be completed within 60 days of the 75 day target," he explained, quoted Monday, July 15.

Muharram appreciated the successful performance of the collaboration between Elnusa and COSL over its collaboration and cooperation so that it could complete these two projects faster than the time target given with excellent acquisition data quality.

Muharam said this project is a very important milestone in the New Venture PHE program in Eastern Indonesia in an effort to obtain new oil and gas exploration blocks to support national energy security going forward.

Using a seismic survey vessel belonging to the second COSL survey, a survey was carried out using the 3D Marine Streamer Broadband seismic acquisition method to get the geometric subsurface structure on the target in' well, particularly in Bone and Seram, which has great potential in terms of oil and gas resources that have not been fully explored.