TULUNGAGUNG - The Tulungagung Regency Government, East Java, said that the rehabilitation or reconstruction of the Junjung Village Junjung Bridge, which had been auctioned with a work value of Rp. 7.5 billion, could be completed in December 2026.
Acting Head of the Road Construction Section of the Public Works and Spatial Planning Office (PUPR) of Tulungagung Regency, Ahmad Rifai Sodik, said the project auction process had been completed and was currently waiting for the completion of the administration from the auction winner before signing the work contract.
"We are still waiting for the auction winner to submit a performance guarantee of five percent of the contract value before the signing," said Sodik in Tulungagung, Antara, Sunday, April 26.
The value of the work contract reached around IDR 7.1 billion, with plans to rebuild the bridge using a girder beam construction that is considered stronger and more durable.
According to Sodik, the project is scheduled to start in May 2026 with a duration of about seven months.
"The target is seven months, so it is expected to be completed in December 2026 and can be optimally functional again," he said.
In addition to the Junjung Bridge, the Tulungagung Regency Government also scheduled repairs to bridges in Pakel District with a budget of around Rp. 900 million.
The project in Pakel is estimated to have a shorter duration, namely about four months, because the scale of the work is smaller. "There are two bridge repair projects this year, namely in Junjung and Pakel," he said.