JAKARTA - The Ministry of Public Works and Public Housing (PUPR) through the Directorate General of Housing has accelerated the construction of landed houses for ministerial positions in the State Capital (IKN) Nusantara.
"The progress of the work for landed houses as Minister at IKN has reached around 10 percent higher than the target plan of eight percent," said Director General of Housing of the Ministry of PUPR Iwan Suprijanto in a statement in Jakarta, Antara, Friday, June 2.
Iwan said that at least 36 units of the Ministerial Position Tax House will be built by the Ministry of PUPR at the 104 Persil location with an area of 10.6 hectares and 105 with an area of 9.1 hectares of the Central Government Core Area (KIPP) IKN.
In addition to the physical construction of landed houses, plant nurseries have also been developed which will later be planted in the Ministerial Position House complex, such as black orchids, guava trees, and others in the existing nursery area (nursery) have been prepared at KIPP IKN.
The Ministry of PUPR appointed a service provider of PT Adhi Karya (Persero) Tbk for operational cooperation (KSO) with PT Cirajasa Engineering Consultant to carry out the construction of the residence.
Meanwhile, the Construction Management package for the Construction of the Ministerial Tax House at KIPP IKN will be carried out by PT Yodya Karya (Persero) - PT Indah Karya (Persero) - PT Surya Perkasa Raya KSO.
The scope of work includes, among others, planning for the design of 104 and 105 parcels, construction work for landed houses, public facilities and social areas for regional infrastructure work and furniture work.
Furthermore, Iwan said that his party had prepared a house design in two types, namely the downslope type and the upslope type with a building area of 580 square meters and a land area of 1,000 square meters.
"This Ministerial Tax House will later be built 2 floors on the first floor will contain a terrace, work room, official waiting room, official area, family living room and also living room. While on the second floor is a private area containing family rooms, main bedrooms, and also children's bedrooms, "said Iwan.
He also added that his party will continue to oversee so that the development process can be carried out properly in the field so that according to the planned and guaranteed the results of quality work with a target of completion in June 2024.
VOIR éGALEMENT:
The English, Chinese, Japanese, Arabic, and French versions are automatically generated by the AI. So there may still be inaccuracies in translating, please always see Indonesian as our main language. (system supported by DigitalSiber.id)
Tags les plus populaires
#Prabowo Subianto #Nouvel An #Syrie #nataru #NatalPopulaire
18 Desember 2024, 07:25
18 Desember 2024, 04:00