JAKARTA - President Prabowo Subianto ordered the Minister of Energy and Mineral Resources (ESDM) Bahlil Lahadalia to take measured steps to ensure that the alternating power outages on part of Java Island do not recur. The instruction was delivered after a limited meeting at the Presidential Palace, Jakarta, Monday, June 22.
The meeting was also attended by the President Director of PT PLN (Persero) Darmawan Prasodjo. The government emphasized the need to strengthen the national electricity system so that similar disruptions do not occur again.
"President Prabowo's instructions to us to immediately ensure that we take measured steps in order to accelerate so that this kind of thing (power outage - red) does not happen again," said Bahlil Lahadalia.
Bahlil Lahadalia explained that there were three main causes that triggered power outages in several areas of Java Island.
The first cause is technical constraints on gas-powered power plants (PLTG) which disrupt the operation of the electricity system.
However, he emphasized that the current electricity system condition has returned to normal. Based on PLN's report, there are no significant disruptions left.
"Starting today, PLN conveyed to me in the meeting that starting today there has been no more disruption. That's according to the CEO of PLN. Because the technical affairs of electricity operational services are with PLN. The government is a regulator," he said.
The second cause is the limited supply of medium-calorific coal needed by PLN for the blending process. PLN's coal needs each year reach around 154 million tons, of which 134 million tons have been contracted.
Meanwhile, the government through the Ministry of Energy and Mineral Resources has tasked mining companies to supply coal to PLN as much as 180 to 190 million tons per year.
However, the specific needs of medium-calorific coal become a challenge in the distribution of supply.
"Which has been contracted by PLN 134 million tons. Actually, in a contract with PLN with entrepreneurs 134 million for one year. Now it's only month 6, it shouldn't be an issue. It turns out that what PLN complains about is the medium calories for blending," he said.
Bahlil Lahadalia said the government had intervened to ensure that the supply of coal according to the needs of the plant could be met.
The third cause is the maintenance process at the power plant. Bahlil asked PLN to accelerate the maintenance of the plant facilities and the network so that the reliability of the system is maintained.
He emphasized that the acceleration of maintenance is important to ensure the quality of electricity services to the community.
"But more than that, we ask PLN to immediately carry out maintenance so that it can really provide certainty of service to the community. I think that," he concluded.