PT Jasamarga Transjawa Tol (JTT) will carry out road reconstruction on the Jakarta "Cikampek" Toll Road (Japek) to increase the comfort of road users and meet Minimum Service Standards (SPM).
Senior Manager Representative Office 1 of PT JTT Amri Sanusi said this reconstruction work would take place at three points, to be precise in lane 1 and lane 2.
"We carry out maintenance activities in the form of road reconstruction which has started from Friday, May 16, 2025 to Saturday, May 24, 2025 at several points of evaluation results," he said in a written statement, Saturday, May 17.
Amri said, during that period, the Jakarta "Cikampek" Toll Road, both towards Jakarta and Cikampek, continued to operate normally.
He added that his party had alerted a number of mitigations during the construction implementation.
"We have prepared mitigation procedures, including diverting the flow of affected traffic before the work area, narrowing the work area, preparing contraflows if the traffic conditions are heavy and coordinating with the Highway Patrol Police (PJR) in traffic management," he said.
For information to road users, he said, his party had carried out socialization through the installation of appeal banners.
"In addition, there is a dynamic message sign (DMS) in the location around the work, both in the direction of Jakarta and Cikampek," said Amri.
Furthermore, Amri apologized for the inconvenience caused by the existence of the work in question.
"We urge all road users to anticipate travel times, ensure that vehicles are in prime condition, have sufficient electronic money balance, charge and fuel before starting the trip," he explained.
また読む:
また読む:
"Always be careful and obey signs, especially around the work location," he concluded.
The details of the date and location of the work on the Japek Toll Road are as follows:
1. Friday, May 16 at 20.00 WIB until Tuesday, May 20 at 09.00 WIB there is road reconstruction at Off Ramp West Karawang 2 Lane 1,
2. Saturday, May 17 at 14.00 WIB until Thursday, May 22 at 10.00 WIB there was road reconstruction at KM 25+815 to KM 26+090, direction Cikampek Lajur 1 and Bahut Luar,
3. Monday, May 19 at 09.00 WIB until Saturday, May 24 at 08.00 WIB there was road reconstruction at KM 38 + 832 to KM 38 +480, towards Jakarta Lane 1 and 2.