JAKARTA - PT PLN (Persero) stated that electricity in Aceh recovered gradually after the 275 kV Muara Bungo-Sungai Rumbai transmission disruption due to extreme weather that affected parts of Sumatra on Friday (22/5).

"PLN continues to accelerate normalization so that the electricity supply in the affected areas can immediately return to the Customer," said PLN UID Aceh Communication & TJSL Manager, Lukman Hakim, quoted by Antara.

Lukman explained that 17 of the total 21 affected substations had been successfully restored as of Saturday at 05:00 WIB.

He said to ensure the repair and normalization of the supply disruption, PLN deployed hundreds of personnel who worked non-stop.

"Currently, the team continues to work hard to ensure that all electricity in Aceh returns to normal after a total blackout due to supply disruptions," he said.

His party asked the public to monitor the development of information through the PLN Mobile application and other official PLN communication channels.

"Please pray from all the people, the team continues to work to normalize and we ensure that the electricity will be normal again," he said.


The English, Chinese, Japanese, Arabic, and French versions are automatically generated by the AI. So there may still be inaccuracies in translating, please always see Indonesian as our main language. (system supported by DigitalSiber.id)