JAKARTA - PT Jasa Marga (Persero) Tbk (JSMR) announced that it will repair roads on the Belawan-Medan-Tanjung Morawa (Belmera) toll road starting today, Monday, July 1 to Saturday, July 6.

Senior Manager Representative Office 1 Jasamarga Nusantara Tollroad Ahmad Fikri said the road repair was in order to meet the Minimum Service Standards (SPM).

"We apologize for the inconvenience caused by the work," Ahmad said in his official statement, quoted Monday, July 1.

He appealed to road users to anticipate travel, ensure that vehicles are in prime condition, have sufficient electronic money balance, refuel before starting the journey and always be careful and obey signs, especially around the location of the work.

"Information about toll roads in the Nusantara Region can be accessed through the social media @jalantolnusantara," he added.

The road repair work is as follows:

1. KM 12 + 217 to 11 + 952 in lane 2 (fast pace) will be held Monday, July 1, 2024 starting at 08.00 WIB to 17.00 WIB.

2. KM 11 + 786 to 11 + 700 in lane 1 (slow lane) will be held on Tuesday, July 2, 2024 from 08.00 WIB to 17.00 WIB.

3. KM 11 + 665 to 11 + 519 in lane 1 (slow rate) will be held on Wednesday, July 3, 2024 from 08.00 WIB to 17:00 WIB.

4. KM 11 + 127 to 10 + 909 in lane 1 (slow lane) will be held Thursday, July 4, 2024 from 08.00 WIB to 17.00 WIB.

5. KM 5 + 995 to 5 + 000 in lane 1 (slow rate) will be held on Friday, July 5, 2024 from 08.00 WIB to 17.00 WIB.

6. KM 10 + 373 to 10 + 223 in lane 1 (slow lane) will be held on Saturday, July 6, 2024 from 08.00 WIB to 17.00 WIB.