The Directorate General of Highways of the Ministry of PUPR said that all sections of the Jakarta Outer Ring Road (JORR) II toll road network will be connected by the end of 2023.
"We connected it to JORR II later this year," said Director General of Highways Hedy Rahadian when met after a Hearing Meeting (RDP) with Commission V DPR RI in Jakarta, on Wednesday, September 6.
Hedy said that a number of toll roads that are part of the JORR 2 network are the Serpong-Cinere Toll Road Section 2 Cinere-Pamulang which was tested for Functional Feasibility (ULF) in May 2023.
Meanwhile, the progress of the Cinere-Jagorawi Toll Road Section 3B has reached 95.66 percent and is targeted to be completed by the end of this year.
Meanwhile, the Cimanggis-Cibitung Toll Road Section 2B Cikeas-Cibitung, as part of the JORR II network, is also targeted for completion this year, with construction progress reaching 73.8 percent.
"It is targeted to be completed this year," said Hedy.
SEE ALSO:
For your information, the JORR II Toll Road Network consists of six toll roads, namely the Kunciran-Serpong Toll Road (11.4 Km), Serpong-Cinere Toll Road (10.14 Km), Cengkareng-Batuceper-Kunciran Toll Road, Cimanggis-Cibitung Toll Road (26.18 Km), and Cibitung-Cilincing Toll Road (34.02 Km).
The presence of the JORR II Toll Road not only strengthens accessibility, transportation efficiency, and reduces congestion, but also triggers economic growth and opens up new business opportunities in the surrounding area.
The English, Chinese, Japanese, Arabic, and French versions are automatically generated by the AI. So there may still be inaccuracies in translating, please always see Indonesian as our main language. (system supported by DigitalSiber.id)