Ahead of the Christmas and New Year's commemoration, PT Industri Telekomunikasi Indonesia (Persero) or PT INTI accelerated the completion of the roofed Solar Power Plant (PLTS) construction in 65 locations with a total power capacity of 485 kWp.

"Alhamdulillah, this project has completed our track record in the energy industry in the past decade," said PT INTI (Persero) President Director Edi Witjara to the media, Tuesday, December 13.

In the project, the Ministry of Energy and Mineral Resources of the Republic of Indonesia, Directorate General of New, Renewable Energy and Energy Conservation, has selected job providers referring to the IEB-P2210-1617461 e-Catalog Package Number.

The construction of the Roof PLTS carried out in 65 locations is spread across various regencies/cities in Indonesia, including:

Kabupaten Banyumas Kabupaten Cilacap Kabupaten Garut Kabupaten Tasikmalaya Kota Pontianak Ketapang Kabupaten JemberCianjur Kota Tangerang Kota Sukabumi Kota Ambon Kota Palangkaraya Kabupaten Murung Raya Jeneponto Takalar Kabupaten Sumenep Kabupaten Gunung Kidul Kabupaten Kabupaten Pangtul Kabupaten Pangkal Pinang Kabupaten Bangka Kabupaten Bangka Kota Medan Kabupaten Cirebon Kabupaten Garut Kabupaten Lanak Kota Singkawang Asahan Kabupaten Kota Kabupaten Kota Baratwaringin Barat Kabupada Palangkaraya Kota Pekanbaru Kabupaten Baru Kabupaten Kampaten Kabupaten Tangerang Kabupaten Sorong Kabupaten Sorong Kabupaten Sorong Kabupaten Tangerang Kabupaten Tangerang Kabupaten Ponorogo Kabupaten Tangerang Kota Tangerang Kota Tangerang Kolakana Utara Kabupaten BanjarbalinggaPang Tangerang Kota Tangerang Selaang Besah Tangerang Belaang Belatung Regency

The target is that the project for the Procurement of the Roof PLTS Development Work Package in the Indonesian Region II for the 2022 Fiscal Year, which was signed on October 21, 2022, can be completed by the end of 2022.

Prior to the construction of the Roof PLTS in 2022, PT INTI (Persero) had also recorded the construction of PLTS with a total power capacity of 7.32 Mega Watt Peak throughout Indonesia, the details are as follows:

2012 : 300 kWp 2013 : 380 kWp 2014 : 295 kWp 2015 : 735 kWp 2016 : 2,160 kWp 2017 : 2,190 kWp 2018 : 1,260 kWp

In addition to PLTS, PT INTI (Persero) is also recorded to have an experience track record in the construction of Solar Energy General Road Lighting (PJUTS) in Sumatra, Java, Sulawesi, Kalimantan, West Nusa Tenggara, and Papua.

"Hopefully, the consistency of PT INTI (Persero) in the development of PLTS and PJUTS can support government programs related to equitable electrification throughout Indonesia," concluded Edi.

The details of the PJUTS development are as follows:

Year 2018: 5,393 points Year 2019 : 3,330 points