Fully Connected 2025, Here's The Latest Progress Of The Bawen-Jogja Toll Road Construction
Illustration of toll road construction (Dok Photo. Ministry of PUPR)

YOGYAKARTA The 75.82 kilometer Bawen-Jogja toll road project is part of the Trans Java toll road that runs from Bawen to Sleman. The toll road project, which started in 2021, will cross two provinces, namely Central Java along 67.05 kilometers and the Yogyakarta Special Region along 8.77 km. So, how is the progress of the construction of the Bawang-Jogja toll road?

For information, the construction of the Bawen-Jogja toll road is divided into six sections, including:

The latest news from the project side states that the construction of the Baban-Jogja toll road section one has reached 36.14 percent as of April 2023 and land acquisition progress of 64.65 percent.

President Director of PT Jasamarga Jogja Bawen (PT JJB), AJ Dwi Winarsa said the construction of the Bawen-Jogja Section 1 toll road will be completed in 2024.

He added that one of the works being carried out is the construction of an elevated bridge in the Mataram Channel. This bridge was made so as not to interfere with the flow of the river so that the flow can still be used by the community.

The inaugural Erection Girder (Bridge Installation) installation plan at the Mataram Selokan location was carried out this month. This work is a process of removing the concrete hashtags that have been produced so that the bridge is installed on the Mataram River," said Dwi in a written statement, quoted Thursday, May 11, 2023.

Regarding land addition activities in DIY, until now it is still at the stage of announcing the nominal list and appraisal activities will soon be carried out.

"The realization of the Compensation Money (UGK) payment is targeted to be completed this year," said Dwi.

As for the special characteristics of land in DIY, up to now it is in the process and waiting for the issuance of palilah fiber and karincing fiber from the Jogja Palace.

Dwi said that his party would continue to coordinate with related parties while waiting for the issuance of palm fiber.

"The construction of the Jogja-Bawen Toll Road will continue to be carried out according to plan," he said.

Dwi emphasized that the construction of toll roads will continue to pay attention to historical aspects of the Ngayogyakarta Palace, cultural heritage sites and ancient ones in the DIY area.

This is information about the progress of the Bawen-Jogja toll road construction. To get other interesting news, keep reading VOI.ID.


The English, Chinese, Japanese, Arabic, and French versions are automatically generated by the AI. So there may still be inaccuracies in translating, please always see Indonesian as our main language. (system supported by DigitalSiber.id)