JAKARTA - The Ministry of Public Works (PU) said that the realization of the 2025 Fiscal Year (TA) absorption of the Ministry of Public Works (PU) had reached 76.11 percent as of December 18, 2025.

This means that in the remaining time, the PU Ministry must rush to absorb the 2025 TA to the target of 96.77 percent.

This was conveyed by the Secretary General of the Ministry of PU Wida Nurfaida in a media briefing on the Preparedness of the Christmas 2025 and New Year 2026 Holiday Infrastructure at the PU Ministry Auditorium, Jakarta, Thursday, December 18.

"So, the progress (realization of the budget) until December 18 at 12.00 from our effective ceiling of Rp. 111.73 trillion, the physical progress is 78.94 percent and the financial progress is 76.11 percent," said Wida.

Although it is still far from the target set, Wida said he was optimistic that his party could achieve the budget realization that had been targeted.

"So, we are still optimistic. These friends of the Directorate General are still optimistic to be able to absorb according to the prognosis target of 96 percent," he added.

Previously, Minister PU Dody Hanggodo revealed that the realization of the budget for the 2025 Fiscal Year (TA) had only reached 56.53 percent as of November 2025. However, the PU Ministry previously targeted the absorption of the 2025 fiscal year to reach 89.03 percent by the end of 2025.

"As for the realization of the budget as of this morning, November 17, 2025 at 08.00, the physical progress reached 61.54 percent, while the financial progress reached 59.06 percent or absorbed Rp64.86 trillion from the total budget of Rp109.81 trillion," said Dody in a Working Meeting (Raker) with Commission V of the DPR RI at the Parliament Complex, Senayan, Jakarta, Monday, November 17.

In more detail, the budget includes the General Secretariat which has been absorbed by 71.96 percent; the Inspector General 71.44 percent; the Directorate General of Water Resources 57.9 percent; the Directorate General of Road Construction 65 percent; the Directorate General of Creative Works 61.7 percent; the Directorate General of Strategic Infrastructure 19.98 percent; the Directorate General of Construction 72.61 percent; the Directorate General of Infrastructure Financing (DJPI) 68.57 percent; the Regional Infrastructure Development Agency (BPIW) 52.55 percent and the Human Resources Development Agency (BPSDM) 76.19 percent.

According to Dody, the addition of funds for the implementation of construction in accordance with the Presidential Instruction (Inpres) in the second semester of 2025 has an impact on the achievement of budget realization.

However, his party is optimistic that it can pursue the realization of the budget until December 2025.

"We report the addition of the budget for the implementation of the Inpres in the second semester also affects the achievement of financial realization. Nevertheless, we are still optimistic that the financial prognosis of the Ministry of PU is projected to reach 96.77 percent by the end of the year," he said.