JAKARTA - All national road networks that were cut off due to natural disasters in the Sumatra region have now recovered. Minister of Public Works (PU), Dody Hanggodo, confirmed that as many as 107 national roads affected by the Sumatra disaster were all back in operation.

The Minister of PU explained that the handling of connectivity infrastructure such as roads and bridges is carried out collaboratively in accordance with the division of authority between the central government and local governments.

"For road and bridge infrastructure which is the authority of the central government, all handling has been successfully completed. Based on the data of the Disaster Response System (Sitaba) of the Ministry of PU as of July 21, 2026, of the 107 national roads affected, all of them have returned to function," said Dody Hanggodo in Jakarta, Friday.

Progress in Handling National Roads and Bridges Reaches 100%

Not only the main road access, the restoration of national bridges also shows significant progress. Of the 43 national bridges affected by the disaster, all have been completed and are back in normal operation. Thus, the progress of handling connectivity infrastructure under the authority of the central government has reached 100 percent.

Update on Handling of Regional Authority Lines

Meanwhile, for infrastructure under the authority of local governments, recovery continues to show a positive trend based on Sitaba data as of July 21, 2026:

Regional Roads: Of the total 2,421 affected road sections, 2,291 road sections have been successfully restored. Regional Bridges: Of the total 1,184 affected bridges, 821 bridges have returned to service.

Next Phase: Permanent Rehabilitation and Reconstruction

Although connectivity access has been reopened, the Minister of PU emphasized that the restoration of this emergency function is not the end of the work. The PU Ministry is now preparing to move to the permanent rehabilitation and reconstruction stage to strengthen the resilience of infrastructure from potential future disasters.

Efforts to improve quality include:

Structural Reinforcement: Permanent repair of road and bridge structures. Drainage System: Capacity improvement and repair of water channels. Slope Security: Slope stabilization and construction of landslide protection buildings.

Carrying the Build Back Better Concept (2026-2028)

The PU Ministry continues to accelerate the post-disaster rehabilitation and reconstruction process in three main areas, namely Aceh, North Sumatra, and West Sumatra provinces.

This step refers to the Master Plan for Rehabilitation and Reconstruction of Post-disaster Sumatra in 2026-2028 by applying the principle of build back better - namely rebuilding infrastructure that is much safer, more resilient, and disaster-resistant.

"Currently, some activities have entered the implementation phase of rehabilitation and reconstruction, while some other works are still in the preparation phase of implementation, completion of technical documents, procurement, and contractual processes," concluded Dody.