JAKARTA - PT Hutama Karya Infrastruktur (HKI) targets that the handling of the Anai Valley access after the Sumatra disaster can be completed in July 2026.
The company noted that currently the progress of handling the land route has reached 73 percent as of the end of May 2026.
"Currently, access to the Anaite Valley has been fully open for 24 hours for both two-wheeled and four-wheeled vehicles, restoring the strategic connection between Padang and Bukittinggi," said HKI Company Secretary Resnu Aditya Wuladarmand in a written statement, Monday, June 22.
Resnumenambahkan, akses Lembah Anai yang saatinitelahdibukapenuhselama24 jamuntukkendaraanrodadua dan roda empat turut mendorong peningkatan volume lalu lintas yang melintasi kawasan tersebut, terutama pada periode libur panjang.
The main works that have been completed include water diversion, river normalization, road body protection, borepile work at several affected points, road body filling, slope reinforcement, channel work and Margayasa Bridge foundation protection.
With the completion of a number of major works, HKI is now focusing on continuing to complete 20 work points with work scopes such as supporting structures, slope handling, road pavement, channels, road safety works, and hotmix asphalt works.
When all the work has been completed, the mobility of the community in West Sumatra can run more smoothly, especially during the long holiday period.
"This road has an important role as a strategic connecting route, so HKI is committed to completing the handling in July 2026, so that the benefits can be optimally felt by the community," he explained.