No New Section Operates This Year, Jasa Marga Will Focus On 5 Toll Projects
Toll road (photo: Antara)

Jasa Marga's Corporate Communication & Community Development Group Head, Lisye Octaviana, said that there are no new toll roads that will operate under Jasa Marga in 2024.

Furthermore, Lisye also said that his party would still focus on five toll projects. Among them are Probolinggo-Banyuwangi, Yogyakarta-Solo, to Yogyakarta-Bawen.

"There is not yet (a new season that will operate). Jasa Marga will focus on five toll projects, now there are South Japek II, Patimban access, Probolinggo-Banyuwangi, Jogja-Solo, and Jogja-Bawen," he said. met at the BUMN Ministry Office, Jakarta, Wednesday, March 27.

Furthermore, Lisye also said that the toll roads could not fully operate. The reason is, some are still in the process of construction to land acquisition.

Actually, in the near future, the first semester does not exist yet. If not there in the near future, everything is still in the process of construction and land acquisition," he explained.

However, Lisye said there are several toll roads under Jasa Marga that will be operated functionally for Eid al-Fitr or Eid al-Fitr 2024 needs.

"There are indeed two functionals for this Eid. Those in Jogja-Solo are already 22.3 km from Colomado to Ngawen. The same position in South Japek is still the same as the previous Christmas period at 8.5 km," he said.

For your information, until the end of 2023, Jasa Marga has a toll road concession of 1,736 km with a length of 1,264 km of toll roads operating. The details consist of 18 sections in Jabodetabek and West Java. Where the two segments are still in the construction stage and one section operates partially.

Selanjutnya, 7 ruas di Jawa Tengah. Di mana dua dalam tanap kontruksi dan satu telah beroperasi sebagian. Kemudian, 6 ruas di Jawa Timur, dimana satu ruas masih dalam tahap kontruksi.

Then, one section in Bali. Then, two segments in North Sumatra, one section in East Kalimantan, and one section in North Sulawesi. All toll roads have been operating.

"Everything (construction stages) is still on schedule. We will try to gradually discuss all of this land and construction. This is per segment per section," he said.