Note, This Is The Schedule For The Portal Rambu Installation On The Jakarta - Cikampek Toll Road
Jakarta - Cikampek (ANTARA) Toll Road

JAKARTA - PT Jasa Marga (Persero) through the Jasamarga Metropolitan Tollroad Regional Division (JMT) as the manager of the Jakarta Cikampek (JMT Area) toll road with PT Jasamarga Tollroad Maintenance (JMTM) as the road maintenance service provider will carry out the Portal Rambu Installation Work on KM 1+500 Jakarta Cikampek Toll Road.

The Portal Rambu Installation Work at KM 1+500 of the Jakarta Cikampek Toll Road will begin on Saturday, November 25 to Sunday, November 26, 2023, with the following stages: - Left Pole Installation at KM 1+500 towards Bandung (will be closed at Bahut Dalam & Lajur 1), held Saturday 25 November 2023 at 18:00 p.m. 20:00 p.m. WIB- Right Pole Installation (median) at KM 1+500 in the direction of Bandung (will be closed at Bahut Dalam & Lajur 4), carried out starting Saturday 25 November at 22:00 p.m. Sunday 26 November 2023 at 00:30 p.m. WIB

The rate used for the work process, meanwhile, cannot be crossed during the work, but other lanes can be used as traffic lanes.

"Jasa Marga and PT Jasamarga Tollroad Maintenance apologize for the inconvenience caused by the work," said Senior Manager Representative Office 2 Jasamarga Metropolitan Tollroad Regional Division (JMT) in a written statement, Saturday, November 25.

He also appealed to road users to always be careful, obey traffic signs, follow directions from officers and arrange travel times, check traffic conditions before traveling and contact the Jasa Marga One Call Center 24 hours at 14080 phone numbers for information about toll roads.