Ahead Of The Rainy Season, Anies' Men Continue To Gerebek Lumpur

JAKARTA - The rainy season is coming soon. In anticipation of flooding due to high-intensity rain, the DKI Provincial Government continues the Gerebek Lumpur program.

Gerebek Lumpur is an effort to dredge mud sediments and garbage massively using heavy equipment. This mud raid was carried out simultaneously in 5 administrative city areas in Jakarta.

The Head of the DKI Water Resources (SDA) Agency, Yusmada Faizal, said that the mud raid activity had been continued since March 24, 2021, for the East Jakarta area, and continued in 4 other city areas in stages from September 2021 to December 2021.

"Starting today, a total of 408 personnel will be deployed in stages from 5 (five) city areas by deploying 46 Amphibious Excavator-type heavy equipment and 123 dump trucks. We are targeting this activity to be completed by December 2021", said Yusmada in his statement, Thursday, 30 September.

Yusmada hopes that the Gerebek Lumpur can reduce the volume of water during the rainy season at times, as well as facilitate the flow of water which is usually clogged with garbage.

"Nevertheless, we also need the role and cooperation of residents to be disciplined in disposing of waste in its place, as well as maintaining environmental cleanliness to prevent puddles during the rainy season", he said.

Public Relations of DKI Jakarta Provincial Government

The following is the schedule and location for the mud raids in each region:

- Central Jakarta

Location: Kali Krukut-Segmen Jl. Bendungan Hilir - Menara Batavia

Work on September 21-December 31, 2021

The dredging yield target is 12,060 m3

Dumping Site in Ancol area

- South Jakarta

Location: Kali Krukut-Segmen Jl. Gen. Sudirman-Jl. Gatot Subroto

Work September 9, 2021 - December 15, 2021

The dredging target is 5,338 m3 with a length of 1.2 km

Dumping Site in Rawa Minyak

- North Jakarta

Location: Kali Sunter, Front Segment of Rawa Badak Pump and Front Segment of Artha Gading Mall

Work has started in approximately one month, targeted for completion in December 2021

The target for the dredging of the Rawa Badak segment is 11,200 m2 with a volume of 17,920 m3, the Artha Gading segment is 8,400 m3

Mud dumping site from the rhino swamp segment in the Beting area, Mud dumping site from the front segment of Artha Gading in Ancol

- West Jakarta

Location of Mookervart River Semanan Segment - Swamp Crocodile

Work on September 13, 2021, and targeted for completion in December 2021

Dredging yield target 36,000 m3

Dumping site in Ancol area

- East Jakarta

Location: Munjul Reservoir

Work March 24, 2021, to December 2021

The dredging target, for dredging the Munjul Reservoir is 44,197 m3

Dumping site at TPU Bambu Apus