Addition Of The Third Lane Of The Cipali Rampung Toll Road In December 2024
JAKARTA - The third lane addition work on the Cikopo 'Palimanan (Cipali) Toll Road will be completed in December 2024.
Reporting from the official Instagram upload of the Toll Road Regulatory Agency (BPJT) of the Ministry of Public Works (PU) @pupr_bpjt, Friday, October 25, this project was worked on by PT Astra Tol Cipali as the Cipali Toll Road Business Entity (BUJT).
The third lane addition was carried out at KM 87 Km 110 Subang Regency, West Java.
The project, which began in July 2024, is a continuation of the addition of the third lane at KM 72'KM 87 and in front of Rest Area KM 101, KM 102 and KM 130 which have been completed in 2023.
As of the 19th week of work, the progress of this increase in lanes has exceeded the target of realization.
"(In) the 19th week with the achievement of 52 percent realization in the KM 87 to KM 98 zone and 46 percent in the KM 98 to KM 110 zone," read the statement in the upload.
SEE ALSO:
Therefore, a daily toolbox meeting is carried out as a form of control of potential hazards and prevention education. In addition, routine readiness of heavy equipment is also carried out.
Routine inspections are also carried out every week to ensure work produces quality according to standards.
"Anyway... I hope the year-end holiday via the Cipali Toll Road is wide, so there are no traffic jams," he added.