JAKARTA - PT Kereta Cepat Indonesia China (KCIC) stated that the longest tunnel project for the Jakarta-Bandung high-speed train tunnel 2 in Jatiluhur, Purwakarta, West Java, has been completed, indicating that 13 tunnels have now been connected.
PT Kereta Cepat Indonesia China Director, Dwiyana Slamet Riyadi, said this success was a joy, especially for the Jakarta-Bandung high-speed rail project.
"This is one of the most important milestones in the process of completing the Jakarta-Bandung high-speed rail project. Today, we have breakthrough tunnel 2", he told reporters in Purwakarta, West Java, quoted from Antara, Tuesday, June 21.
Previously, the construction of tunnel 2 with a length of 1,040 meters was one of the construction points that had high challenges because it was located in clay or clay shale. This tunnel project was completed on June 17, 2022.
This type of soil has characteristics that are easily weathered when exposed during excavation so it has the potential to cause movement of the embankment construction and the road above it.
The clay soil is classified as extreme because if exposed to water and air it can reduce up to 80 percent of the carrying capacity of the soil.
"Tunnel 2 is one of the toughest obstacles in the construction of the Jakarta-Bandung high-speed rail project because the geological conditions are filled with clay shale", explained Dwiyana.
KCIC carried out several mitigations by adding excavations that were originally two points to four points. In addition, the company also added workers to increase the number of layers from three layers to nine layers to avoid excavation collapse.
KCIC covered the tunnel walls and roof with double sheet walls to strengthen the tunnel, thereby slowing down project work.
VOIR éGALEMENT:
Dwiyana said that the investment progress of the Jakarta-Bandung high-speed rail project has reached 84 percent, while the physical progress has reached 76 percent. The commercial operation target is targeted for June 2023.
In November 2022 KCIC will conduct dynamic tests to conduct trials of Electric Multiple Units (EMU). The EMU series is targeted to arrive in Indonesia in September.
Chinese Ambassador to Indonesia, Lu Kang, said the progress of the Jakarta-Bandung high-speed rail project was important for Indonesia's diplomatic relations with China.
He said that the President of Indonesia and the President of China are very concerned about this transportation project because every time they communicate they always discuss the Jakarta-Bandung high-speed rail project.
"We are working together on the Jakarta-Bandung high-speed rail project in the form of strengthening Indonesia's relations with China. In the future, we can also work together better", concluded Lu Kang.
The English, Chinese, Japanese, Arabic, and French versions are automatically generated by the AI. So there may still be inaccuracies in translating, please always see Indonesian as our main language. (system supported by DigitalSiber.id)