The government through the Ministry of Public Works (PU) has accelerated the repair of the national bridge in Meureudu, Pidie Jaya Regency, Aceh, which was damaged by flash floods last week with plans to increase labor.

"Adding the number of tools and labor (to accelerate)," said Commitment Making Officer (PPK) 1.2 BPJN AcehRita Marlenidi Pidie Jaya, Tuesday, December 9, as reported by ANTARA.

He explained that so far the repair process has almost reached the top level or reached the bridge and is targeted for completion on Friday, December 12, 2025.

"If there are no obstacles, December 12, the functional (can be passed)," said Rita Marleni.

The bridge recovery work, he said, deployed seven excavators, two wheel loaders, one vibro compact unit, and 19 lever trucks.

In an effort to accelerate, he said, his party also plans to add heavy equipment to labor so that work is completed more quickly.

"Adding heavy equipment and security personnel, and for the next stage of installing the boulder," said Rita Marleni.

He said the handling of boulders could later be carried out simultaneously on a pile of Class B and Class A aggregates, because so far it is as high as a bridge.

"On the field, intense cooperation and coordination, so that currently there are no obstacles, it has been resolved," said Rita Marleni.