JAKARTA - PT Hutama Karya Infrastruktur (HKI) reported that the progress of the construction of the 18.5-kilometer Betung Jambi Toll Road' has reached 80 percent by March 2025.
"As of the end of March 2025, the progress of the Betung Toll Road Jambi Section IV has reached 80 percent," said Director of Operations III of HKI Aditya Novendra Jaya in a written statement, Friday, April 25.
In the construction process carried out, HKI uses several technologies that help facilitate project work such as terrestrial laser scanners.
The purpose of using this tool is to create 3D models and measurements of the volume of concrete structures. This technology has high accuracy in measurements as well as detailed and precise documentation.
In addition to the use of the terrestrial laser scanner, the construction of the Betung Toll Road Jambi Section IV also implements photogravities to document the progress of the construction that was built as well as for the progress opname of soil pile work. The use of this photogrammetry has an advantage of faster and wider acquisition of topographic data.
SEE ALSO:
If the Betung Toll Road Jambi Section IV is operated, it can later speed up the trip from Tempino to Pijoan or vice versa which initially took approximately one hour to about 30 minutes.
The toll road will also be connected to the Betung 'Jambi Section III Toll Road, which is now operating.
"We hope that prayers and support from the entire community so that the process of building the Betung Toll Road Jambi Section IV can be carried out smoothly and provide optimal benefits for the community," he added.