JAKARTA - As one of the National Strategic Projects (PSN), the Serang 'Panimbang Toll Road in Banten Province continues to be carried out. The toll road is targeted to be completed in full by 2026.

The Toll Road Regulatory Agency (BPJT) of the Ministry of Public Works (PU) said that the Serang 'Panimbang Toll Road is a liaison for the Tanjung Lesung Special Economic Zone (SEZ). The project is expected to increase connectivity and encourage Banten's economic growth.

"As one of PSN, the Serang 'Panimbang Toll Road is an important link to the Tanjung Lesung Special Economic Zone. This infrastructure is expected to strengthen connectivity, encourage Banten's economic growth and open access to leading tourism in the southern region," wrote the upload of the official Instagram account @pupr_bpjt, quoted Monday, August 25.

The total length of the toll road is known to reach 83.66 kilometers (km). The details are Section 3 CilelesPanimbang along 33 km with the support of the State Budget construction.

Section 2 Rangkasbitung Cileles reached 24.17 km and Section 1 Serang Langkasbitung 26.5 km which was already operating in December 2021.

"Seksi 1 Jalan Tol Serang 'Panimbang saat ini telah beroperasi, sementara pembangunan dilanjutkan pada section 2 dan section 3," ujar BPJT.

Later, the toll road will also be connected to the Trans Java (Tangerang 'Merak) toll road network, thereby streamlining logistics, supporting tourism and encouraging equal distribution of regional development.

The toll road also crosses four regencies/cities, namely Serang City, Serang Regency, Lebak Regency and Pandeglang Regency.

To note, the construction of Section 2 of Rangkasbitung Cileles has reached construction progress of 89.15 percent with an achievement of 86.59 percent land acquisition. The section is targeted to be completed in the first quarter of 2026.

Meanwhile, the construction of section 3 of Cileles 'Panimbang includes three phases. For phase 1, currently the construction progress has reached 97.7 percent, with a land acquisition achievement of 93.32 percent. The completion target is in the first quarter of 2026.

As for phase 2, construction progress has reached 36 percent with the achievement of land acquisition of 93.32 percent. Phase 2 development is targeted to be completed in the fourth quarter of 2026.

As for phase 3 or finally, the construction progress has reached 28.8 percent with the achievement of land acquisition of 93.32 percent. Development in this phase is targeted to be completed in the fourth quarter of 2026.