JAKARTA - Medco E&P Grissik Ltd (Medco E&P), together with SKK Migas recorded positive results from work-over activities of Sumur Suban-22ST2 in Corridor Block, Musi Banyuasin Regency, South Sumatra.
Production test results showed an additional 9 MMSCFD of gas, well exceeding the initial target of 2 MMSCFD.
President Director of Medco E&P, Ronald Gunawan, said that this achievement is a form of synergy and effectiveness in the implementation of the well optimization program.
We are grateful for this success. Suban-22ST2 results prove that optimizing existing wells through a more precise technical approach and operational efficiency can contribute to increasing national production," he said, Tuesday, November 18.
He added that the rework activities were carried out rigidly, allowing for a faster and more efficient process.
The work lasted for 12 days and was completed on November 10, 2025.
SEE ALSO:
Sementara itu, Kepala Satuan Kerja Khusus Pelaksana Kegiatan Usaha Hulu Minyak dan Gas Bumi (SKK Migas) Djoko Siswanto menyampaikan rasa syukurnya atas keberhasilan KKKS PT Medco E&P Grissik Ltd telah melakukan kegiatan kerja ulang (work over) pada sumur pengembangan Suban-22ST2.
Proyek yang dimula dimulai pada 30 Oktober 2025 ini dinyatakan selesai pada 10 November 2025, bertepatan dengan hari Pahlawan.
“Keberhasilan kegiatan kerja ulang (work over) Sumur Suban-22ST2 di Blok Corridor dengan potensi tambahan gas sebesar 9 MMSCFD akan memperkuat pasokan gas nasional dan mendukung program ketahanan energi,” tandas Djoko.
SEE ALSO:
Meanwhile, Head of the Special Task Force for Upstream Oil and Gas Business Activities (SKK Migas) Djoko Siswanto expressed his gratitude for the success of KKKS PT Medco E&P Grissik Ltd in carrying out work-over activities at the Suban-22ST2 development well.
The project, which started on October 30, 2025, was declared complete on November 10, 2025, to coincide with Heroes' Day.
"The success of Suban-22ST2 Sumur workover activities in Corridor Block with an additional gas potential of 9 MMSCFD will strengthen the national gas supply and support the energy security program," said Djoko.