Here's The Progress Of Adding The Third Lane On The Cipali Toll Road
SUBANG - Astra Tol Cipali is currently doing a third lane addition work on the Cikopo 'Palimanan (Cipali) Toll Road.
Precisely, the addition of the third lane was carried out at KM 87 KM 110 Subang Regency, West Java.
The project to improve road quality and increase capacity that has been going on since July 2024 is a continuation of the addition of the third lane at KM 72'KM 87 and in front of the KM 101 Rest Area, KM 102 and KM 130 which has been completed in 2023.
Based on VOI's direct observation at the project site on Tuesday, November 12, the addition of the third lane was carried out on the far right.
Previously, the barrier between lanes at KM 87 'KM 110 was a filing of clothes or wire rope and there was vacant land in the middle planted with ornamental plants.
However, at this time, with the addition of lanes, the barrier between lanes was changed to a concrete wall.
While at the location, there were still a number of work for the vulnerability and asphalting of the 23-kilometer additional lane project.
SEE ALSO:
Corporate Communications & Sustainability Management of PT Lintas Marga Sedaya Ardam Raff Trisilo said that until the end of October 2024, the progress of the lane widening work had reached 52 percent.
He is optimistic that the work can be completed in early December.
"All of them from KM 87 to KM 110 at the end of last month (the progress) was 52 percent. Hopefully, it will be around the second week of December," he said.