PLN Fully Operates 275 KV Muara Enim' Gumawang SUTET
JAKARTA - PT PLN (Persero) has successfully fully operated the Muara Enim Extra High Voltage Air Line (SUTET) 275 kilovolts (kV) and two Extra High Voltage Substations (GITET).
These two infrastructures are known to contain a Domestic Component Level (TKDN) of more than 90 percent.
The operation was marked by the provision of a second line of voltage (energy) connecting Muara Enim-Gumawang by the PLN of the Southern Sumatra Development Main Unit (UIP SBS) on Saturday, November 2, after previously the first line was successfully operational on May 7, 2024.
PLN's New Renewable Project and Energy Management Director, Wiluyo Kusdwiharto explained, the operation of the Muara Enim-Gumawang 275 kV SUTET will further strengthen the electricity system on the island of Sumatra, especially the South Sumatra and Lampung regions. With this, he believes the existing capacity will be able to meet every community needs.
"The development of this infrastructure is proof that PLN together with the Government continues to strive to provide reliable and sufficient electricity supply for the entire community, especially on the island of Sumatra," said Wiluyo, Wednesday, November 6.
General Manager of PLN UIP SBS, Zaky Adikta, said that the construction of the 275 kV Muara Enim-Gumawang SUTET consisting of 325 towers and spread over 117.1 kilometers was connected by system to the 275 kV Sumatra Electric Toll Road which crosses Muara Enim Regency, Ogan Komering Ulu Regency, and East Ulu Ogan Komering Regency.
This SUTET will be operated as an electricity backbone line in South Sumatra Province supported by GITET 275 kV Muara Enim and GITET 275 kV Gumawang 3x250 megavolt ampere (MVA) to support the Southern Sumatra subsystem which currently has a peak load of 2,512 megawatts (MW).
Zaky added that the completion of this infrastructure could not be separated from the role of all stakeholders involved.
SEE ALSO:
He ensured that the construction process that had been carried out went smoothly with the implementation of the Work Safety and Health Principle (K3) consistently.
In addition, the construction of the National Strategic Project infrastructure was successfully completed with high TKDN content, reaching 90.92 percent for the Muara Enim SUTET 'Gumawang 275 kV and 70 percent for GITET 275 kV Muara Enim and GITET 275 kV Gumawang.