State Palace And Garuda IKN Enter The Furniture Installation Stage, Targeted For Completion August 10
JAKARTA - Minister of Public Works and Public Housing (PUPR) as well as Acting Head of the Archipelago Capital Authority (OIKN) Basuki Hadimuljono revealed the latest progress of IKN development in East Kalimantan.
Through the Instagram upload of the Ministry of PUPR @kemenpupr, it is explained that the construction of a number of infrastructures continues. One of them is the construction of the State Palace and Garuda Palace, which has a progress of 95 percent.
Currently, the two buildings are in the furniture installation stage and are targeted for completion on August 10.
"The progress of the State Palace and Garuda Palace infrastructure has reached 95 percent. Currently, both are in the furniture installation stage and are targeted for completion on August 10," wrote Instagram @kemenpupr, Saturday, August 3.
Meanwhile, the road network in the Central Government Core Area (KIPP) which has been paved is 7 kilometers (km). Then, the road to the State Palace and the Garuda Palace which will be functional along 1,260 meters (m) has been tightened.
"The road network in KIPP with asphalt conditions is 7 km long and the work road has been compacted. The road to the State Palace and Garuda Palace which will be functional along 1,260 meters has been tightened," he said.
Furthermore, from the 4 Offices of the Coordinating Ministry (Kemenko) each with 4 towers will function during the 79th Anniversary of the Republic of Indonesia at IKN on August 17, 2024, there will be 7 towers.
The details are the Coordinating Ministry for 1 (1 tower), the Coordinating Ministry for 2 (1 tower), the Coordinating Ministry for 3 (2 towers) and the Coordinating Ministry for 4 (3 towers).
"ASN units will be functional at least 8 towers with each tower consisting of 60 residential units and the Ministerial Position Tax House (RTJM) will function 14 units complete with furniture," he said.